2, prohibited in the spiral steel pipe around the storage area of steel erosion of the items;
3, spiral steel pipe bottom should be high, strong, smooth, to prevent the material damp or deformation;
4, the same kind of material according to the storage have been stacked;
5, open-air stacked spiral steel pipe, the following must have wooden mat or stone, stacking a slight tilt to facilitate drainage, and pay attention to the material placed flat to prevent bending deformation;
6, SSAW steel pipe stacking height, artificial homework of not more than 1.2m, mechanical homework of not more than 1.5m, stacking width of not more than 2.5m;
7, between the stack and the stack should leave a certain channel, check the road is generally 0.5m, access channel depending on the material size and transport machinery may be, generally 1.5 ~ 2.0m;
8, open piling steel and channel should be placed, that is, mouth down, I-beam should be put, the steel I channel surface can not be up, so as not to water rust;